Task Objective
Capture Month-to-Month (MTM) leases and scheduled expirations for the next 12 months from the Lease Expiration Detail report and enter them in the PPP workbook.

1 Prerequisites / Tools

Report PacketLease Expiration Detail (next 12-month range, correct property)
WorkbookPPP open to current month tab

2 Step-by-Step Instructions

  1. Verify property & date range.

    Header must show correct Property, Fiscal Period = current month, and As-Of date = today. Report range should cover the next 12 months.

    Verify property & date range.
  2. Record Month-to-Month (MTM) count.

    At the top of the report locate the MTM Leases section and note the total unit count.

    Record Month-to-Month (MTM) count.
  3. Enter MTM count in PPP.

    Type the MTM total into PPP row MTM Leases.

    Enter MTM count in PPP.
  4. Identify monthly scheduled expirations.

    Scroll to the Monthly Summary table → note each month’s Scheduled Expirations count (next 12 months).

    Identify monthly scheduled expirations.
  5. Enter expirations row in PPP.

    In PPP row Scheduled Lease Expirations, enter each month’s count under its corresponding column.

    Enter expirations row in PPP.
  6. Locate NTV / Eviction move-out dates.

    In the detail section, find residents with Notice to Vacate or Eviction status; record the expected move-out month.

    Locate NTV / Eviction move-out dates.
  7. Verify move-out month accuracy.

    Ensure each expected move-out date falls in the correct month column (e.g., examples shown all fall in Jul 2025).

    Verify move-out month accuracy.
  8. Understand NTV > Expiration variance.

    The monthly Notice to Vacate (NTV) total can exceed scheduled expirations because it also counts MTM residents choosing to leave and early terminations.

    Understand NTV > Expiration variance.

3 Escalation & Support

System error / report unavailableSubmit Help-Desk ticket ➜ notify RM
Behind schedule (after 11:15 AM)Inform RM; provide progress status

4 References

PPP Playlist – All Steps
Next WI ➜ Maintenance Review (PPP-007)

5 Revision History

DateVer.DescriptionAuthor
2025-09-08v1.0Initial releaseS. Rea

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article