SOP ID ▸ BMM-FIN-PPP v1.0 | Last Rev 2025-09-08
Owner (Role) | Regional Property Manager |
Effective | 2025-09-08 |
Next Review | 2026-03-08 |
Typical Duration | ≈ 30 min (≤ 45 min after heavy leasing weekends) |
SOP Layer Document
TABLE OF CONTENTS
- PPP | Property Performance Plan – Weekly Update SOP
PPP | Property Performance Plan – Weekly Update SOP
Purpose
Ensure each Property Manager opens the week by completing the PPP Excel workbook (financial baseline) and delivering it to the Regional Manager before noon every Monday. This is the very first task of the week—without exception.
1 Scope & Triggers
Applies to | All Bellaire properties using PPP workbook + RealPage. |
Trigger | 09:00 AM CST every Monday. |
Completion Window | Share with RM by 11:30 AM; must be finalized by 12:00 PM CST. |
2 RACI Matrix (Responsible, Accountable, Consulted, Informed)
Role | R | A | C | I |
---|---|---|---|---|
Property Manager (PM) | ✅ | |||
Regional Manager (RM) | ✅ | |||
Director of Property Management (DPM) | ✅ | |||
President | ✅ (only if major delays/issues) |
3 Inputs / Outputs
Inputs | RealPage reports & dashboards (see Section 5); prior-week PPP workbook. |
Outputs | Updated PPP workbook saved ➜ emailed to RM (and owners after RM review). |
4 Process Overview (Swim-lane)
PM ──► 09:00 Start → Run 10 reports → Transpose to PPP → Save file │ │ └─────────────────────► Email RM (11:30) ───┘ RM Receives → Review (data OK?) → Forward to Owners │ ▼ If issue ➜ Return to PM for fix
5 Procedure – Sequential Steps (collapsed)
1. Open PPP workbook ▸ identify today’s column
Path: Teams Drive › Financial › PPP › 2025.
Select current-month tab → locate column with today’s date.
1. Open PPP workbook ▸ identify today’s column
Path: Teams Drive › Financial › PPP › 2025.
Select current-month tab → locate column with today’s date.
2. Run 10 RealPage reports ▸ transpose data to PPP
Run each report in the exact order below and copy the indicated data points into the PPP workbook.
(see Job Aids PPP-002 … PPP-011 for click-paths and screenshots)
- Boxscore Summary
- Delinquent & Prepaid
- Leasing Activity Detail
- Results & Decisions
- Lease Expiration Detail
- Lease Expiration Bar Chart
- Maintenance Review
- Availability
- Total Billed & Collected
- Lease Trade-Outs
2. Run 10 RealPage reports ▸ transpose data to PPP
Run each report in the exact order below and copy the indicated data points into the PPP workbook.
(see Job Aids PPP-002 … PPP-011 for click-paths and screenshots)
- Boxscore Summary
- Delinquent & Prepaid
- Leasing Activity Detail
- Results & Decisions
- Lease Expiration Detail
- Lease Expiration Bar Chart
- Maintenance Review
- Availability
- Total Billed & Collected
- Lease Trade-Outs
3. Save PPP as “PPP-{{PropertyCode}}-YYYY-MM-DD.xlsx”
Keep in the same property folder; overwrite if re-run the same day.
3. Save PPP as “PPP-{{PropertyCode}}-YYYY-MM-DD.xlsx”
Keep in the same property folder; overwrite if re-run the same day.
4. Email workbook to RM ▸ subject “PPP YYYY-MM-DD – {{Property}}”
Attach file and send by 11:30 AM CST.
4. Email workbook to RM ▸ subject “PPP YYYY-MM-DD – {{Property}}”
Attach file and send by 11:30 AM CST.
5. RM reviews ▸ approves or returns for correction
If data aligns with owner targets → forward to Owners list.
If discrepancies → reply to PM with corrections needed.
5. RM reviews ▸ approves or returns for correction
If data aligns with owner targets → forward to Owners list.
If discrepancies → reply to PM with corrections needed.
6 KPIs & Compliance Metrics
On-time completion | 100 % by 12:00 PM CST every Monday. |
Accuracy | 0 discrepancies flagged by owners or RM per week. |
7 Escalation – KPI Out-of-Tolerance
Condition | Action |
---|---|
Not started by 09:15 | PM texts RM for support. |
Workbook not shared by 11:30 | Auto-ping RM + DPM (Google Chat). |
Still incomplete at 12:00 | RM escalates to DPM; PM logs root-cause. |
Major data error after owner send-out | DPM informs President; corrective plan required. |
8 References
ID | Title |
---|---|
PPP-001 | Workbook Prep & Naming Convention |
PPP-002 | Report Guide - Boxscore Summary |
PPP-003 | Report Guide - Delinquent & Prepaid |
PPP-004 | Report Guide - Leasing Activity Detail |
PPP-005 | Report Guide - Results & Decisions |
PPP-006 | Report Guide - Lease Expiration Detail |
PPP-007 | Report Guide - Lease Expiration Bar Chart |
PPP-008 | Report Guide - Maintenance Review |
PPP-009 | Report Guide - Availability |
PPP-010 | Report Guide - Total Billed & Collected |
PPP-011 | Report Guide - Lease Trade-Outs |
PPP-012 | Handoff & Owner Notification |
9 Revision History
Date | Version | Description | Author |
---|---|---|---|
2025-09-08 | v1.0 | Initial release | S. Rea |
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article